Africanian
  • Home
  • News
  • News 24/7
  • Business
  • Sports
  • World
    • US
    • Russia
    • Europe
    • Asia
    • America
  • Events
No Result
View All Result
Africanian
  • Home
  • News
  • News 24/7
  • Business
  • Sports
  • World
    • US
    • Russia
    • Europe
    • Asia
    • America
  • Events
No Result
View All Result
Africanian
Home Business

Kenya news: Kenyans to pay more over Ketraco delayed projects

A number of court cases involving wayleave acquisition and contractor claims as well as some land owners who cannot be traced, means that State agency will always have its hands full

Kenya news: Kenyans to pay more over Ketraco delayed projects
Share on FacebookShare on TwitterShare via Whatsapp

Auditor-General Nancy Gathungu has sounded the alarm that Kenya Electricity Transmission Company (Ketraco) may be exposed to unforeseen project cost overruns due to ongoing court cases, wayleave acquisition and contractors claims.

The report on Ketraco’s financial statements for the year ending June 30, 2019, says claims go beyond original contract period amounting to Sh12.97 billion.

The audit warns that in the event that these contingent liabilities come to pass, Ketraco, a public company, may be exposed to unforeseen project costs resulting in inability to meet its obligations when they fall due.

“This may affect service delivery capacity of the company,” says the report signed by Ms Gathungu and currently before the National Assembly.

It will be considered by the House committee on Public Accounts (PAC) chaired by Ugunja MP Opiyo Wandayi.

This comes as it emerges that the electricity transmission company has Sh3.40 billion in outstanding compensation to land owners for wayleave.

Budgetary allocation

The delays in clearing the amount have been attributed to lack of budgetary allocation from the National Treasury and long talks between land owners, the company and various county governments.

Delays in compensating project affected persons may expose the government to legal suits, cost escalations and project delays.

Completion of the Sh1.8 billion 220 KV Turkwel-Ortum-Kitale substations also hangs in the balance after the contractor was liquidated.

The project financed by the Exim Bank of India, was entered into in April 2013 with an expected completion date of June 30, 2018.

However, in July 2018, the courts in India ordered liquidation of the contractor, which resulted in financial challenges that made the firm unable to complete the project.

The audit notes that by the time of liquidation, the contractor had achieved an overall completion status of 78 percent.

The audit notes, another contractor is in the process of being identified as a replacement to take over the remaining works.

“The project may experience delays in completion as well as associated cost overruns,” the audit says.

Ms Gathungu has also flagged the construction of the 132 kilometre of the 400KV double circuit transmission line from Lessos substation in Nandi, Kenya to Tororo substation in Uganda.

The report notes that the project awarded to Instalaciones Inabensa S. was a joint venture between Ketraco and African Development Bank effective from September 20, 2010 but in April 2016, the contract was terminated for nonperformance and on December 31, 2017, the loan agreement expired.

At the time, the project, which is already behind schedule, was at 61 percent completion level.

By the time the loan agreement was expiring, the loan account had an undrawn balance of Sh2.72 billion with no evidence whether the loan agreement had been renewed.

Sh101.8m legal fees

This means that delivery of services to the intended beneficiaries may not be achieved.

However, on July 30, 2019, the tribunal hearing the matter awarded Instalaciones Inabensa S. Sh4.5 billion in breach of contract although Ketraco has sought the assistance of Attorney-General Kihara Kariuki to have the award set aside on account that it is against the public interest.

The delay in resolving the matter for the past three years has seen Ketraco spend a staggering Sh101.8 million on legal fees.

“In the circumstances, it is not certain whether the project will be completed in the near future. It is likely to incur additional costs and losses which the Government of Kenya may suffer in the event it is not completed,” the report warns.

The audit also notes significant delays by Ketraco in completing four of the projects under its implementation as enumerated several times in previous audit reports.

Initiatives facing significant delays are the 220KV and 132KV transmission lines and substations projects, power transmission system improvement project, multinational Kenya- Tanzania power interconnection project and Kenyan section of the interconnection project of electric grids of Nile Equatorial lakes countries project.

Source: nation.africa/kenya

RelatedPosts

Somalia transforms Doolow with a plan to support vulnerable households

Somalia transforms Doolow with a plan to support vulnerable households

December 4, 2025
Spain: Three women lead global innovation and communications at ReactID

Spain: Three women lead global innovation and communications at ReactID

November 28, 2025
Visa boosts global payments in USDC through Aquanow integration

Visa boosts global payments in USDC through Aquanow integration

November 28, 2025
Ghana transforms its agriculture thanks to Joshua Toatoba’s Model

Ghana transforms its agriculture thanks to Joshua Toatoba’s Model

November 20, 2025
Clean water restores dignity to rural communities in The Gambia

Clean water restores dignity to rural communities in The Gambia

November 10, 2025
DRC: Maluku, the new industrial zone driving resilience

DRC: Maluku, the new industrial zone driving resilience

November 7, 2025
Afriex and Visa Direct accelerate $669B in Remittances with Real-Time Payments

Afriex and Visa Direct accelerate $669B in Remittances with Real-Time Payments

November 6, 2025
NEPAD-IPPF: 20 years connecting Africa and transforming lives

NEPAD-IPPF: 20 years connecting Africa and transforming lives

November 5, 2025
Brazzaville gears up to shine in 2026

Brazzaville gears up to shine in 2026

November 4, 2025
Africanian News Is a dedicated project aimed at amplifying the voices of the African Ecosystem and Diaspora. We actively collaborate with initiatives to improve access to education and digital inclusion, both in traditional schools and through digital platforms, for African children.

It’s crucial to emphasize that none of the articles or images featured on our platform are intended for copyright infringement, neither now nor in the future.
If you believe that any information, text, image, etc., may be subject to copyright and should be removed, please notify us by sending an email to: [email protected]

News Categories

  • America (39)
  • Asia (131)
  • Business (1,232)
  • Culture (227)
  • Destinations (210)
  • Europe (153)
  • Food and Drink (14)
  • Guides & Tips (20)
  • Health (629)
  • Hotels (5)
  • Meetings and Tech (349)
  • News (2,534)
  • Opinion Piece (12)
  • Russia (73)
  • Science (62)
  • Sports (311)
  • Style (4)
  • Travel (145)
  • US (107)
  • World (422)

Your dreams matter; your stories matter.

Feel free to explore collaboration opportunities with us. Share your articles, thoughts, interviews, experiments, or no-comment videos by reaching out to [email protected].

You can also subscribe to our mailing list to receive the latest updates from Africanian News.

Newsletter

© 2025 Africanian News.

Log In

Sign In

Forgot password?

Don't have an account? Register

Forgot password?

Enter your account data and we will send you a link to reset your password.

Back to Login

Your password reset link appears to be invalid or expired.

Log in

Privacy Policy

Accept

Add to Collection

  • Public collection title

  • Private collection title

No Collections

Here you'll find all collections you've created before.

No Result
View All Result
  • Home
  • News
  • Business
  • Sports
  • Meetings and Tech
  • World

© 2025 Africanian News.